Gate/Activity |
Description |

Click Image to Enlarge
|
G-12:
Project Start |
|
Designate
Program Sponsor and Project Manager
|
Project
Start begins with the designation of a Program Sponsor and Project
Manager. The Program Sponsor is designated by OCE. The Program Manager
assigns the Project Manager.
|
G-11: Project Strategy
Lock-Down
|
-
Business Objective:
Approve a set of
features and project strategy
-
Owner: Project Manager
-
Review Board:
Program Sponsor,
Program Manager, Project Manager, Contracting Organization(s), and
Performing Organization(s)
|
Project Manager
|
The
Project Manager is responsible for ensuring that the documents indicated
in the next activity are completed with quality and meet the acceptance criteria
defined in the Release Planning Procedure (SOP 1005))
|
Organizations:
-
Project
Sponsor
-
Contracting
-
Performing
|
Program Sponsor (OWN)
-
Project
Strategy including: Timeline, R&D Budget, Affordability Percentage,
Scope of Work definitions and Anchor Objectives.
Contracting Organization
(OWN)
Performing Organization
(OWN)
|
Project Manager
|
The Project Manager
establishes a preliminary project plan incorporating the project strategy
and high-level effort estimates received within this gate. Once the above
documents are accepted by the receiving organization the Project Manager
will call the Review Board to session and provide evidence that all
requirements have been met for Gate 11.
|
Review Board
|
Establish
project strategy and the initial project constraints of scope, cost and
schedule utilizing such factors as R & D Budget, Affordability Models
and Anchor Objectives.
Upon
approval, all materials are communicated to the Contracting and Performing
Organizations. The
communication is focused at the approved anchor objectives, project
strategy, initial project constraints and scheduling. The Project Manager
is responsible for communications to all participating project areas.
|
Click Image to Enlarge
|
G-10: Requirements
Scope Lock-Down
|
-
Business Objective: Approve the Scope of
Work for which the organization will commit to develop requirements.
-
Owner: Project Manager
-
Review Board: Program Sponsor,
Program Manager, Project Manager, Contracting Organization(s), and
Performing Organization(s)
|
Project Manager
|
The
Project Manager is responsible for ensuring that the following documents
are completed with quality and meet acceptance criteria defined in the
Release Planning Procedure (SOP 1005).
Contracting
Organization (OWN)
Performing
Organization (OWN)
|
Review Board
|
Review
the results of the concept phase and commit to the definition and planning
of a project. Target delivery
windows may be established, but this does not constitute a commitment to
deliver the project as it is defined at this point.
The additional definition and planning which takes place during the
definition phase will increase knowledge about the scope, cost and
schedule of the project which may result in changes to any or all of those
parameters.
|
Review Board
|
The
Review Board’s acceptance of the approved documents by the Receiving
Organization moves each SOW document to the Development Function of the
Performing Organization for analysis.
|
Project Manager
|
The
Project Manager ensures coordination between Contracting and Performing
Organizations. Project
Managers facilitate meetings and document meeting outcomes. This effort is focused at reducing cycle time and
maintaining the highest level of common understanding between parties.
Further, the Project Manager will refine the project plan
incorporating data available.
|
G-9:
Definition Phase Plan Approved
|
-
Business Objective: Approve the plan to execute the
definition phase so that the project’s business requirements (scope,
timeframe and cost) are met
-
Owner: Project Manager
-
Review Board: Program Sponsor,
Program Manager, Project Manager, Contracting Organization(s), and
Performing Organization(s)
|
Project Manager
|
The
Project Manager is responsible for ensuring that the following documents
are completed with quality and meet acceptance criteria defined in the
Requirements Definition Procedure (SOP 1040).
|
Organizations:
|
In
order to complete the plan for the Definition Phase, the Project Manager
requests and receives the items listed below from various areas of both
the Contracting and
Performing Organizations. Acceptance
criteria for each item listed are defined in the Requirements Definition
Procedure (SOP 1040).
Contracting
and Performing Organizations (CON)
-
Detailed
Schedule
-
Resources/Costs
Assigned
-
Capital
Budget
-
Risk
Plan Developed
Validation Function of the
Performing Organization (CON)
Operations Function of the
Performing Organization (CON)
|
Project Manager
|
The
deliverables for G-9b contribute to the development of the project’s
communication plan and project plan by the Project Manager. At this point
the Project Manager ensures that all known assumptions, dependencies,
constraints, and risks are reflected in the project plan.
The
Project Manager sends recommendations to minimize the impact from
assumptions, dependencies, constraints, and risks to the Program Sponsor.
The Program Sponsor supports the resolution and/or mitigation of
project barriers by working with OCE and/or Unit Managers.
|
Click Image to Enlarge
|
G-8: System
Requirements Definition Approved
|
-
Business Objective: Obtain approval of
the system requirements definition(s) from the Contracting Organization(s).
-
Owner: Project Manager
-
Review Board: Program Manager,
Project Manager, Contracting Organization(s), and Performing
Organization(s)
|
Project Manager
|
The
Project Manager facilitates the dialog necessary between all parties that
participated in the definition of SOW documents for the Development
Function of the Performing Organization to complete Systems Requirements
Specifications.
The
Project Manager has responsibility for ensuring full disclosure of
features, functionality and technical constraints that impact the project
scope approved at Gate 10.
|
Review Board
|
The
Review Board reviews the approved System Requirements Specifications.
|
G-7: Lock-Down Level
Estimates Complete
|
-
Business Objective: Complete the
estimates and scope refinement necessary for Lock-Down.
-
Owner: Project Manager
-
Review Board: Program Manager,
Project Manager, Contracting Organization(s), Architecture Function of the
Performing Organization(s), and Development Function of the Performing
Organization(s)
|
Project Manager
|
The
Project
Manager is responsible for ensuring that the documents in the next
activity are
completed with quality and meet acceptance criteria defined in the
Requirements Definition Procedure (SOP 1040).
|
Organizations:
|
Performing Organization
(OWN)
Architecture Function of the
Performing Organization (OWN)
Development Function of
Performing Organization (OWN)
|
Project Manager
|
The
Project Manager ensures coordination between Contracting and Performing
Organizations. This effort is
focused at reducing cycle time and maintaining the highest level of common
understanding between parties.
Further,
the Project Manager will refine the project plan for the release
incorporating data provided through this gate. The Project Manager will
communicate the final portfolio scope to all interested areas in the
organization
|
Click Image to Enlarge
|
G-6: Project Lock-Down
(Also described as:
Go/No Go Decision or Cross-functional Commitment to the Delivery of a
Defined Set of Features and Functionality)
|
-
Business Objective: Obtain commitment
between the Performing Organization(s) and the Contracting Organization(s)
for the delivery of a defined project scope of work within a defined
timeframe. (This scope is a refinement of the G-10 scope/plan).
-
Owner: Project Manager
-
Review Board: Program Sponsor,
Program Manager, Project Manager, Contracting Organization(s), Performing
Organization(s), and Service Organization
|
Project Manager
|
The
Project
Manager is responsible for ensuring that the documents in the next
activity are
completed with quality and meet acceptance criteria defined in the
Requirements Definition Procedure (SOP 1040).
|
Organizations:
-
Project
Manager
-
Contracting
-
Performing
|
Project Manager (OWN)
Contracting Organization
(OWN)
Performing Organization
(OWN)
|
Project Manager
|
In
order to complete the project plan, the Project Manager will request and
receive materials listed in G-6d from various areas of both the
Contracting and Performing Organizations.
Acceptance criteria for each item listed are defined in the
Requirements Definition Procedure (SOP 1040).
|
Organizations:
|
Contracting and Performing
Organizations (CON)
Program Sponsor, Contracting
and Performing Organizations (SUP)
QA Function of the
Performing Organization (CON)
Operations Function of the
Performing Organization (CON)
|
Review Board
|
The
Review Board reviews the results of the definition phase and re-evaluates
the business objectives of the project.
This review may result in agreed upon changes in scope, cost and/or
schedule. The resulting
agreement represents a commitment between the Performing and Contracting
Organizations to deliver the project as defined within the agreed upon
scope, cost and schedule constraints.
|
Project Manager
|
The
Project Manager ensures coordination between the Contracting and
Performing Organizations. Further,
the Project Manager communicates the project scope and schedule to all
interested parties.
|

|
G-5: Detailed Plans
Complete
|
-
Business Objective: Approve the detailed
project plan and commit the appropriate resources to execute the plan.
-
Owner: Project Manager
-
Review Board:
Project Sponsor,
Program Manager, Project Manager, and Performing Organization
|
Project Manager
|
The
Project Manager is responsible for ensuring that the documents in the next
activity are completed with quality and meet acceptance criteria defined in the
Detail Design Procedure (SOP 1041).
|
Performing
Organization
|
Development Function of the
Performing Organization (OWN)
Architecture Function of the
Performing Organization (OWN)
-
Allocated
Requirements
-
System
Interfaces
The Architecture Function of
the Performing Organization includes the Development and Operation
Functions since they share responsibility for delivery and support of the
delivered solution. Development
handles the creation of the interface code.
Operations manages the receipt, processing and storage or interface
data; this includes service level considerations for capacity, turnaround
time, and connectivity.
|
Project Manager
|
In
order for the Project Manager to complete the project plan, he/she will
use the project plan from the Development Function of the Performing
Organization to update the overall project plan.
Acceptance criteria are defined in the Detail Design Procedure (SOP
1041).
|

Click Image to Enlarge
|
G-4: Begin Validation
|
-
Business Objective: Ensure that the
product meets the defined project scope and that the quality of the
product is at an acceptable level to proceed to the Validation phase.
-
Owner: Validation Function
of the Performing Organization(s)
-
Review Board: Program Manager,
Project Manager, Validation function of the Performing Organization(s),
and Development Function of the Performing Organization(s)
|
Project Manager
|
The
Project Manager is responsible for ensuring that the documents and actions in
the next activity are completed with quality and meet acceptance criteria
defined in the Release Planning (SOP 1005), Training and Documentation
(SOP 1101) and Quality Function procedures (SOP 1210).
|
Performing
Organization
|
Development Function of the
Performing Organization (OWN)
-
Product
(contains all defined scope and under configuration management)
-
Development
testing results
-
Systems
integration results
-
Preliminary
product documentation
-
Field
performance criteria
Validation Function of the
Performing Organization (OWN)
Note: Gate 4 requires a
formal management review by the Performing Organization.
|
Review Board
|
Before
commencing validation, the quality of the product and documentation
emerging from the development phase is evaluated by the Review Board to
assess the risk associated with entering the next phase. The level of management involved at this review may be
lower than at the other management phase reviews since the issues being
addressed at this review are internal to the Performing Organization.
A key consideration at this review is to determine whether the
product and documentation quality is high enough to allow the testing
function to make significant ress. It is also possible at this review
that decisions may need to be made concerning scope, cost and schedule
tradeoffs if the project performance to date has deviated from the
baseline established at G-6. Such
decisions should not, however, be deferred until this point in the
project’s lifecycle but should be actively addressed as soon as the need
for a decision becomes apparent.
At
any point in the life cycle, if there are decisions concerning scope, cost
and schedule tradeoffs, the Gate 6 Review Board will formally review the
situation.
|
Project Manager
|
Should
the Gate 6 Review Board need to assemble, the Project Manager is
responsible for scheduling, notifying participants, creating meeting
materials, facilitating meetings and distributing meeting minutes for this
formal Review Board meeting. The Project Manager updates any resulting
changes to the project plan. This
may lead to the request and collection of revised estimates from
Performing, Contracting, and Service Organizations.
|

Click Image to Enlarge
|
G-3: Begin System
Certification
(Product Acceptance
Testing)
|
-
Business Objective: Approve release of
the product to System Certification Testing.
-
Owner: Contracting
Organization(s)
-
Review Board: Program Manager,
Project Manager, Contracting Organization(s), System Certification Function of the Contracting Organization(s), and Validation Function of
the Performing Organization(s)
|
Project Manager
|
The
Project Manager is responsible for ensuring that the validation testing in
the next activity is completed with quality and meets acceptance criteria defined in
the Training and Documentation Procedures (SOP 1101) and Quality Function
Procedures (SOP 1210).
|
Validation
Function of the Performing Organization
|
The
Validation Function of the Performing Organization completes a review and
validation of the Preliminary Documentation provided by the Development
Function of the Performing Organization.
Acceptance by the Validation Function of the Performing
Organization is required prior to beginning system certification.
|
Project Manager
|
The
Project Manager has responsibility for verifying completion and obtaining
signoff from the Validation Function of the Performing Organization.
|
Click Image to Enlarge
|
G-2: Begin
FOA/Beta
(Client Acceptance
Testing)
|
·
Business Objective: Approve release of
the product for first office application.
·
Owner: Contracting
Organization(s)
·
Review Board: Project Sponsor,
Program Manager, Project Manager, Contracting Organization(s), System
Certification Function of the Contracting Organization(s), Performing
Organization(s), Validation Function of the Performing Organization(s),
and Service Organization
|
Project Manager
|
The
Project Manager is responsible for ensuring that the documents and actions
in the next activity are completed with quality and meet acceptance criteria
defined in the Quality Function Procedure (SOP 1210).
|
Organizations:
-
Performing
-
Contracting
-
Support
-
Training
|
Development Function of the
Performing Organization (OWN)
Validation Function of the
Performing Organization
Contracting Organization
Training Organization
Service Organization
|
Review Board
|
Gate
2 requires a formal management review.
The Deployment Phase represents a significant milestone to the
customers in the lifecycle of a project.
There is also significant risk associated with this milestone. The project product is expected to be of commercial
quality at this time and any data from the validation phase that indicates
otherwise must be carefully analyzed in terms of its potential impact to
the selected customer site. Options at this review include approval to deploy the
project product, approval to deploy with exceptions due to some subset of
the scope having failed validation, and approval of a schedule delay (and
consequent additional cost) to correct problems that are known to exist.
|
Project Manager
|
Deviations
in deliverables or timeframe are handled using a formal process with the
results communicated by the Project Manager to all areas participating in
the effort.
Any
decisions concerning scope, cost and schedule tradeoffs, the Gate 6 Review
Board shall formally review the situation.
Should the Gate 6 Review Board need to assemble, the Project
Manager is responsible for scheduling, notifying participants, creating
meeting materials, facilitating meetings and distributing meeting minutes
for this formal Review Board meeting. The Project Manager updates any
resulting changes to the project plan.
This may lead to the request and collection of revised estimates
from Performing, Contracting, and Service Organizations.
|

Click Image to Enlarge
|
G-1: Begin Controlled
Rollout
|
-
Business Objective: Approve the release
of the product for controlled rollout. This gate is only required when a
controlled rollout (CRO) is planned as an integral phase of the project.
-
Owner: Contracting
Organization(s)
-
Review Board: Project Sponsor,
Program Manager, Project Manager, Contracting Organization(s), Performing
Organization(s), and Service Organization
|
Project Manager
|
The Project Manager is
responsible for ensuring that the documents and actions in the next
activity are
completed with quality and meet acceptance criteria defined in the
Training and Documentation (SOP 1101) and Deployment and Post
Implementation procedures.
|
Organizations:
|
Performing Organization
(OWN)
-
FOA
test results
-
Service
training
-
Client
acceptance
Contracting Organization
(OWN)
|
Project Manager
|
Since
a controlled rollout occurs in the production environment, the documents
in G-1b must meet quality and acceptance criteria defined in the Training
and Documentation (SOP 1101) and Deployment and Post Implementation
Procedures (SOP 1220). When a
controlled rollout is an integral phase of the project plan it is
mandatory, otherwise, this gate is optional.
|
Click Image to Enlarge
|
G-0
|
-
Business Objective: Approve the release
of the product for general availability.
-
Owner: Contracting
Organization(s)
-
Review Board: Project Sponsor,
Program Manager, Project Manager, Contracting Organization(s), Performing
Organization(s), and Service Organization
|
Project Manager
|
The
Project
Manager is responsible for ensuring that the documents and actions
in the next activity are completed with quality and meet acceptance criteria
defined in the Deployment and Post Implementation procedures (SOP 1220).
|
Organizations:
-
Contracting
-
Service
-
Performing
-
Training
|
Contract Organization (OWN)
Service (OWN)
Performing (OWN)
-
Service
training
-
FOA
test results
-
Order
entry system
-
Client
acceptance
Training (OWN)
|
Review Board
|
Gate 0 requires a formal
review process. It is the
final management phase review that occurs upon completion of initial field
deployments (First Office Application and Controlled Rollout) which are
intended to provide final validation of the project product in a live
system environment. This
review effectively marks completion of the project and acceptance by the
Contracting Organizations from the Performing Organization.
The
Review Board reviews and approves completion of the Gate 0
requirements. Deviations in
deliverables or timeframe are handled by convening the Gate 6 Review
Board. This group will make any decisions concerning scope, cost,
and schedule tradeoffs.
|
Project Manager
|
Should the Gate 6
Review
Board need to assemble, the Project
Manager is responsible for scheduling, notifying participants,
creating meeting materials, facilitating meetings and distributing meeting
minutes for this formal Review
Board meeting. The Project
Manager updates any resulting changes to the project plan.
This may lead to the request and collection of revised estimates
from Performing,
Contracting, and Service Organizations.
The Project Manager is
responsible for attending the Program/Project
Management post implementation review on the project and holds a
meeting with other Program and
Project Managers to review lessons learned.
Trends and issues encountered over a number of projects are
discussed as wells as new techniques that proved successful.
|
Performing
Organization
|
The Validation Function of
the
Performing Organization conducts a project post-implementation
review in which representatives from all areas participating in the
project review the project. Quality
issues and their root cause are discussed.
The Quality Assurance group documents the post implementation meeting
and distributes to all attendees, all
Project Managers and ram
Managers as well as the PMO.
|